The Interim Measures on Acceptance and Operation Management of Provincial Energy use Monitoring Platform for Public Buildings

Source: International Energy Agency
Last updated: 17 May 2021

These measures are to provide a standardised guideline for the development, operation and inspection of provincial public building energy consumption monitoring platforms. The guideline specifies criteria and steps for pre-acceptance and acceptance. The acceptance process consists of the followin steps:

  • Testing the software functions of the monitoring platform to form a system test report;
  • Reviewing the report on the construction and operation of the monitoring platform;
  • Reviewing the relevant documents of the construction process of the monitoring platform and the report on the use of funds;
  • Checking the status and condition of the data center;
  • Spot checks on the monitoring and transmission of building sub-item measurement data;

Acceptance conclusion by the expert group.